TS 16949
Emergency Plan
Division
Thermonex
Hall
B15
Place
Pirmasens
Date of issue
09.05.2006
Editor
H. Hofmann
Date of amendment
Emergency Plan Thermonex Pirmasens Plant.doc 17.08.06 Page 1
Emergency Case
Assessment
Action
1
Breakdown:
· Software and/or Hardware failure of machine control
· Failure of a major equipment component
· Three independent running production units are available.
· Each adhesive formulation can be produced on each production unit.
· Connecting an alternative Computer
· Switch to another production unit
2
· Compressed Air
· Two independent running compressors are available. One is sufficient to run the production.
· Maintenance on a yearly based contract.
· Plant maintenance is able to repair air pressure system themselves.
3
· Power supply
· Internal system
· External system
· Production breakdown
· Safety stock for important products.
· Connecting a mobile current generator
· Plant maintenance is able to repair power supply themselves.
4
· Discontinuance of raw material supply
· Defined minimal stock level of raw material, packing units and finished products.
· Safety stock for important raw materials and packing units.
· Fast raw material supply within the Forbo-Group is possible.
5
Outbreak of Fire:
· Raw Material Stock
· Finished Products Stock
· Production Units
· External raw material stock.
· External stock for finished products.
· Outsourcing production to other Forbo plants.
6
· ERP-System (Hardware and/or Software)
· Available in defined space of time.
· Data backup on external server.
· Production and deliveries without IT Service.
· Maintenance contracts.
7
· Heating system
· Contract with long heating supplier (EVU) exists.
· Plant maintenance is able to repair heating system themselves.
8
· Unplanned (above average) absence of production staff members.
· Additional production line for water based products exists in the Pirmasens plant.
· Moving staff members from other production units.